Asset Health Analytics Community
The Asset Health Analytics Community will share and explore asset health analytics use cases to help... View more
Unanswered Questions During August 2022 Community Conversation
-
Unanswered Questions During August 2022 Community Conversation
Hello Asset Health Analytics Community Members,
Thank you again to everyone who took time to attend our August Community Conversation yesterday! Because we ran out of time at the end, I had to take a few questions offline but I heard right back from our speaker Jennifer and have provided answers below. If you think of any additional questions for Jennifer, please either touch base with me directly at kpraet@utilityanalytics.com or reply to this post below:
Question 1: Are you able to shift or adjust project dates in this, or say yes or no to the project?
Answer: Yes, there is a status on each project for tracking them. We are working with 1898 to review the list of status choices to better fit our workflow process going forward. This will allow us to change the year of a project or cancel one project for another.Question 2: What type of projects were most chosen through this process? Circuit Rebuilds? Laterals? URD Cable Replacement? Secondary Network projects?
Answer: Since my group provided the budget targets, the model selects the projects with the highest benefit cost ratios to meet the budget in each year. The types of projects with the highest benefit cost ratios were feeder projects and lateral projects.Again if you think of any additional questions for Jennifer please let me know.
Thanks again!
——————————
Kevin Praet
Membership Coordinator
Utility Analytics Institute (UAI)
Boulder CO
315-440-3033
——————————
Sorry, there were no replies found.
Log in to reply.